Cloverpatch Switchback – Wednesday, July 19th:
We’re going to tackle that super-nasty poison oak covered switchback on Cloverpatch trail by adding a crib wall. This improvement is crucial to make the trail more rideable for everyone. We’ll be harvesting most of the materials near the site to keep things convenient. Meet up at the Lowell Covered Bridge at 8:00 am.
Cloverpatch Connector Bridge Work – Sunday, July 23rd:
Our focus for this day will be finishing the sill pads and placing the sills for the Cloverpatch Connector Bridge. If time permits, we’ll also lift and place the first stringer onto the sills. Additionally, some of the trail crew will be working on finishing tread and rock work on corners. Meet up at the Lowell Covered Bridge at 8:00 am.